Select the true statement regarding currencies.

Select the true statement regarding currencies.

Select the true statement regarding currencies.

A.
Only one base currency is supported per database.

B.
Currencies are updated daily per exchange rates.

C.
Only 10 currencies are supported in Primavera.

D.
Only two currencies are supported in Primavera.

Explanation:
The base currency is the monetary unit used to store cost data for all
projects in the database and is controlled by a global administrative
setting in the Project Management module. The default base currency
for Primavera is US dollars ($). The view currency is the monetary unit
used to display cost data in Primavera and is controlled by a user
preference.
Note: All costs are stored in the Based Currency. All costs are stored in the Base Currency and all
other Currencies are calculated values using the Base Currency value and conversion rate.