Identify the business case that would support the creation of OBS elements to align with WBS
elements within individual project plans.
A.
Legal/regulatory requirements that prohibit users from seeing data across functional areas
maintaining smaller sets of project data
B.
Mitigate the risk of significantly variant project management skill levels across an organization
C.
Large projects with multiple cross-functional learns that will be responsible for
updating/maintaining one set of project data
D.
Supporting data export/import process to minimize risk of degrading schedule quality
Explanation:
A work breakdown structure (WBS) is a hierarchical arrangement of the products
and services produced during and by a project. The project is the highest level of the WBS while
an individual activity required to create a product or service is the lowest level. Each project in the
enterprise project structure (EPS) has its own WBS.When creating a project, the project manager typically develops the WBS first, assigns work
products and documents to each WBS element, and then defines activities for performing the
element’s work. Specific earned value calculations can be specified for each WBS element, along
with an organizational breakdown structure (OBS) element responsible for all work included in the
WBS element.