Your customer’s project teams are cross-functional and global. Therefore, any standard reports
must be generated at a standing day/time so that all affected resources and users have clearly
defined timelines for data quality checks prior to report creation. Identify the P6 R8 feature that will
address this requirement.
A.
Email monthly report to distribution list
B.
Send reports directly to printers at all user locations
C.
Schedule report generation to minimize performance issues
D.
Post generated reports to content repository
Explanation:
Reports can be run on the spot or scheduled.
Note: Reports may be set to run on a schedule. This is very handy if you need a set of
reports all generated at the same time. For example, you may need reports showing
data as of the 25th of the month available for a review meeting the following day.You can schedule a set of reports to run at 11:59 pm on the 25th. They can then be
automatically e-mailed to all meeting participants. In this sense, scheduled reports
are similar to the batch reports of P6 Professional, but with the added bonus that you
can schedule the delivery.