What is the significance of the “Summarize project based on detailed activity resource
assignments” setting?
A.
Summarized project data will reflect top-down plans.
B.
Summarized project data will reflect bottom-up plans.
C.
Summarized project data will reflect integrated actuals.
D.
Summarized project data will be monetized.
Explanation:
Use the Detail Activity Resource Assignments option for in-progress projects when
you want to review detailed activity-level summarized data, for example, for earned value
reporting.
Note: ‘Summarize Project Based on’ determines whether the Summarizer calculates and displays
rolled-up data based on resource assignments at the activity or project level.
Note 2: You can summarize project data to a specific WBS level when calculating and maintaining
summary data.