What is the significance of the "Summarize project based on detailed activity resource assignments" setting?

What is the significance of the “Summarize project based on detailed activity resource
assignments” setting?

What is the significance of the “Summarize project based on detailed activity resource
assignments” setting?

A.
Summarized project data will reflect top-down plans.

B.
Summarized project data will reflect bottom-up plans.

C.
Summarized project data will reflect integrated actuals.

D.
Summarized project data will be monetized.

Explanation:
Use the Detail Activity Resource Assignments option for in-progress projects when
you want to review detailed activity-level summarized data, for example, for earned value
reporting.
Note: ‘Summarize Project Based on’ determines whether the Summarizer calculates and displays
rolled-up data based on resource assignments at the activity or project level.
Note 2: You can summarize project data to a specific WBS level when calculating and maintaining
summary data.