You are a project manager addressing risk responses in your Risk Register. As you created your
Risk Register, you also created multiple mitigating/response plans for each risk. Identify the
functionality that will indicate which response plan is primary.
A.
Response plan marked Active
B.
Response plan with the closest start date
C.
Response plan with lowest cost
D.
Response plan marked highest priority
Explanation:
Response Plan row: Create one or more response plans while you are in the
planning phase and indicate the response type. When you have analyzed your response options,
choose one response plan by selecting the Active option next to the appropriate response plan.
In the example below, two response plans have been created for the Concrete supply constrained
risk. The first plan is to accept the risk and take no action; the second plan is to reduce the impact
of the risk by contracting with alternative suppliers. You can see this second plan was selected as
the plan of choice.Note:
* A risk register and risk scoring matrix provide a system for monitoring and
tracking risks.
* Rather than having a single response, you can create multiple responses to a risk.
* Once you have established your risks, you can view the Probability and Impact
Diagram, which shows how the risks are coded. Several pre-defined PID matrices
have been provided from which we can choose.
Reference: Oracle Primavera P6, Working with Risk Response Plans