Where are risk response plans captured?
A.
In the Risk Scoring Matrix
B.
In the Activity Notebook for Risk
C.
In the Risk Register
D.
In the Project Notebook for Risk
Explanation:
The Response Plans detail window is the area in the risk register where you create
plans for handling the identified risks. Once you have identified which project risks need further
action, create a response plan and assign response plan action items for each risk to reduce the
negative impact on the project.
Example below:Reference: Oracle Primavera P6, Working with Risk Response Plans