You are an implementation consultant responding to the requirement that a cost account structure
be set up in Primavera to be able to receive actual costs incurred by each contributing
organization. There is also a cost account structure set up in the customer’s financial management
system (FMS).
What would be the easiest long-term recommendation for setup and maintenance of the cost
account structure?
A.
Set up a cost account structure in Primavera that mirrors the FMS, and manually manage
changes.
B.
Set up a cost account structure in Primavera and a global project code to map to FMS for
Integration.
C.
Do not set up the cost account structure, and receive costed actuals only from the FMS.
D.
Set up integration between Primavera and the FMS to maintain all ongoing costing data.
Explanation:
It refers to the existence, in the structure, to the cost account structure for FMS.
Integrate Primavera P6 EPPM with the Financial Management system.
B