You are an application administrator. You received a change request to alter the relationship
between an EPS node and its associated OBS element.
What would be a prudent course of action to complete before moving forward with this change?
A.
Merge the old OBS element with the requested OBS element.
B.
Create a new OBS element per the change request.
C.
Determine which users would be affected.
D.
Delete the old OBS element per change request.
Explanation:
Users might be affected.
Note: The OBS and EPS are interconnected such that the OBS can be used to apply security
roles and access all projects below specific EPS elements.