What duration type should be used?

An activity is to be completed within a fixed time period and the total effort is also fixed. What
duration type should be used?

An activity is to be completed within a fixed time period and the total effort is also fixed. What
duration type should be used?

A.
Fixed Units

B.
Fixed Duration and Units/Time

C.
Fixed Units/Time

D.
Fixed Duration and Units

Explanation:
For Fixed Duration & Units, the duration and units remain constant as the units/time
are changed. Use this duration type when the activity must be completed within a fixed time period
and the total amount of work is fixed.