Cost accounts are hierarchical, and___________.
A.
are assigned in the project details
B.
are created and managed at the project level
C.
are applicable to all projects in the EPS
D.
are assigned to users with security
Explanation:
In primavera P6 we can create cost accounts and associate them with activity
resource assignments or expenses in a project. Cost accounts are hierarchical, and they enable
you to track activity costs and earned value according to your organization’s specific cost account
codes.
Reference: Oracle Primavera P6 Cost Account