What does Schedule Preview do?
A.
Provides print preview functionality
B.
Calculates the new forecast dates
C.
Reschedules but does not finalize until Save
D.
Reports on multiple projects without opening them
Explanation:
About Schedule Preview
After modifying activity, relationship, and assignment data, but before deciding to formally
schedule a project, use the optional Schedule Preview feature to estimate schedule changes
without actually committing them to the project. Schedule Preview automatically recalculates the
schedule for activities that have changed or were affected by a change to a relationship, resource
assignment, or another activity. You can then decide to commit these changes to the schedule or,
if the preview produces unwanted results, discard them. If Schedule Preview is disabled, changes
to activities are not reflected in the schedule until you manually calculate the schedule again.