What are two benefits of designating a resource as inactive?
A.
All project history and costs are retained.
B.
Budgets from past projects will remain intact.
C.
The associated user’s information will be automatically deleted.
D.
Actual costs for past projects will be positively affected.
E.
The resource is identified as unable to perform future work.
Explanation:
Non-active resources may have left the organization but are not deleted from the
system since they may have actual hours. Reference: Field Map for Oracle Primavera P6
Reporting Database