Identity the true statement regarding the Must Finish By constraint.

Identity the true statement regarding the Must Finish By constraint.

Identity the true statement regarding the Must Finish By constraint.

A.
The Must Finish By constraint is used as the starting date for the backward pass.

B.
The Must Finish By constraint forces all activities in the project to finish by that date.

C.
The Must Finish By constraint affects the total Role limits for the project.

D.
All activities have negative total float when a Must Finish By constraint is assigned.

Explanation:
Must Finish date is not constraining Activity. It is used to calculate the schedule on
“Backward pass” to show the float whether negative or positive. If Must finish date is less than
current project finish date then some critical activities will be showing negative float but if current
project finish date is less than must finish date then it will show all positive float.
Note: Primavera calculates the backward pass starting from the end date of the project finish date
you enter manually. Therefore, if the end date is not possible to be achieved using the network
logic that you have made, then you will always get negative total float