What is the significance of setting “Summarize project based on high-level resource planning”?
A.
Summarized project data will reflect top-down plans.
B.
Summarized project data will reflect bottoms-up plans.
C.
Summarized project data will reflect actuals pushed from another application.
D.
Summarized project data will be monetized.
Explanation:
Typically, use the High Level Resource Planning option for future projects that are
currently planning only high-level resource allocation requirements, or for projects that are
underway, but for which you do not want to assign resources at a detailed activity-level.
Note: ‘Summarize Project Based on’ determines whether the Summarizer calculates and displays
rolled-up data based on resource assignments at the activity or project level.Note 2: You can summarize project data to a specific WBS level when calculating and maintaining
summary data.