Which activity coding solution would serve the needs of the project managers in your programs?

You are a program manager for a group of 10+ projects. You actually have a dedicated node for
each program, and your owned projects reside under each node. Each program has its own
unique requirements for viewing activity data.
You do not want to ask for activity codes that would be visible to the entire organization. Which
activity coding solution would serve the needs of the project managers in your programs?

You are a program manager for a group of 10+ projects. You actually have a dedicated node for
each program, and your owned projects reside under each node. Each program has its own
unique requirements for viewing activity data.
You do not want to ask for activity codes that would be visible to the entire organization. Which
activity coding solution would serve the needs of the project managers in your programs?

A.
Create global activity codes.

B.
Create user activity codes.

C.
Create project activity codes.

D.
Create EPS activity codes.

Explanation:
EPS activity codes can be used only in projects that belong to a specified EPS,
including its subordinate EPS nodes, if any.
Note:
* An activity code can be designated as one of three types: Global, EPS, or project.
* Activity Codes can be defined through the Administer | Enterprise Data
dialog, where they can be set at the Global, EPS, and Project level. Activity
codes help to sort, filter, and group activities.
* Some data can be stored either at the enterprise level, or at the project
level. One such example is activity codes. Some activity codes may be enterprise,
perhaps CSI codes to identify the type of work. Others, such as the specific floor in
a multi-story construction, are particular to one project and meaningless in others.
Reference: Oracle Primavera P6, What are codes?