Select two true statements regarding calendars.
A.
Global calendars are available to a subset of projects.
B.
Project calendars are available for the current project.
C.
Only a limited number of calendars can be created.
D.
Resource calendars are applied to all resources with the same primary role.
E.
Activity type determines whether the activity uses resource calendars when scheduling.
F.
Activity calendars are managed by individual users/resources.
Explanation:
B: Project calendars can only be used within a specific project, and can be
assigned to activities within the project. A project can also have a default
calendar, which may be either a project calendar or a global calendar.
E: A resource calendar is designed to work for a specific resource. Furthermore, calendars can be
assigned to activities and to the resources assigned to that activity.
Note: Calendars describe the time available for project work. A calendar can be defined at
three levels: global, project, and resource.