You are a project manager with a required monthly update cycle. You have marked actual start
and actual finish dates for your Physical % complete activities, with % complete calculated from
activity steps. You schedule and summarize your project plans. However, your activities are not
showing 100% complete. What is the problem?
A.
Your security does not allow you to update Activity Status.
B.
You did not save the changes made to the activities.
C.
You have not completed each of the activity steps.
D.
You must refresh the view in the web to view the changes.
c