What data will you be highlighting?

You are meeting with a customer and demonstrating the Resource Assignments GANTT view.
What data will you be highlighting?

You are meeting with a customer and demonstrating the Resource Assignments GANTT view.
What data will you be highlighting?

A.
Tabular-formatted data showing codes and attributes

B.
Timescaled resource assignment data

C.
Timescaled project and resource data

D.
Timescaled cost and resource data

Explanation:
Note: See 5a below.
Customizing the Resources Assignments Gantt Chart Bars
Customize the settings for the Gantt chart view on the Resources Assignments page. You can set
features for up to three bars per assignment.
To customize the resource assignments Gantt chart bars:
Note: Set at least one bar to Current Bar.
* Current Bar – Shows a bar that spans the early start date/actual start date to the early finish
date/actual finish date for each assignment. For a Current bar, you can select an additional option
for showing the progress of activities.
* Late Bar – Shows the late start date to the late finish date of an assignment. A Late bar does not
display if the project has not been scheduled.
* Plan Bar – Shows the planned start date to the planned finish date of an assignment. This bar is
used for simulating the outcome of the project schedule as part of project planning.
Etc.
Reference: Oracle Primavera P6, Customizing the Resources Assignments Gantt Chart Bars