Identify the key benefit of the Plan Resources view.
A.
You can create resource staffing scenarios using waterline analysis.
B.
You can identify staffing shortfalls within detailed project plans.
C.
You can view and analyze resource allocation without assignments to activities.
D.
You can view and assign resources mapped to appropriate roles with the highest skills.
Explanation:
Note:
* You can delete a financial period that has high-level assignment planning values (as entered on
the Plan Resources page of P6) as long as the financial period does not contain past period
actuals. When you delete a financial period that has high-level assignment planning values, the
values are deleted as well.
* View options for including assignments made in the Plan Resources view in other allocation
related view in Primavera