Identify the true statement regarding Schedule Checker.
A.
Before running Schedule Checker, you should schedule the project.
B.
Schedule Checker evaluates the WBS structure to demonstrate standards compliance.
C.
Schedule Checker is run from the Portfolios section.
D.
Run Schedule Checker before scheduling the project to fix issues.
Explanation:
Note: The new schedule checker is a tool that assists planners, project managers and the PMO to
ensure project plans are built within the guidelines of industry and organizational best practices.
The schedule checker performs a 14-point analysis to ensure that activities and dependencies of
the project schedule are following desired standards. The schedule checker adheres to the DCMA
14-point assessment check and produces a report that lists all opportunities for corrective action or
improvement when aspects of the project schedule fall outside the quality guidelines. The report
includes a summary and detailed sections displaying activities falling outside your configured
thresholds.
Note 2: The Schedule Checker can be run against one or multiple projects. You can save the
thresholds to run again for the project that is open.
The first thing to do is set up the 14 Configurable User Thresholds. See figure below.Example of output.
Shown below is the top half of the Schedule Check Summary Report.Reference below the lower half of the Schedule Check report.