Select two objectives of the OUM Manage Project Execution and Control phase.
A.
Manage the project resources to deliver on time and in budget.
B.
Gain project acceptance.
C.
Release staff.
D.
Execute against the Project Management Plan.
Explanation:
Integration of the Manage focus area phases with the Implement focus area phases is illustrated below:
Note:
The Manage focus area has three phases:
* Project Start Up Phase
* Project Execution and Control Phase
* Project Closure Phase
Reference: OracleUnified Method (OUM) Oracle’s Full Lifecycle Method for Deploying Oracle-Based
Business Solutions