What is true about Iteration Plans in OUM Manage?

What is true about Iteration Plans in OUM Manage?

What is true about Iteration Plans in OUM Manage?

A.
They cover a single project.

B.
They focus on achieving iteration’s objectives and reducing risks

C.
They are flexible and can change at any time.

D.
They are used to plan the subsequent phase of the project.

Explanation:

During each iteration, the current Iteration Plan is adjusted. Subsequent Iteration Plan is created
prior to the iteration beginning.
Note:
* There are two plans active in the project at any given time – the implementation plan and the
iteration plan.



Leave a Reply 1

Your email address will not be published. Required fields are marked *


Margarita

Margarita

Don’t think it’s right…
Iteration plan is not used to plan the “next phase”, but the next iteration is planned before it begins.

I would say it’s B.

ITERATION PLANNING Iteration planning is where the bulk of the planning for a project occurs. Each iteration should be planned such that a set of specific objectives are accomplished and a group of project risks are addressed.