What is the purpose of the Project Execution and Control Phase?
A.
To prove the solution described in the scope document meets the project requirements.
B.
To provide adequate visibility into actual progress so that management can take effective actions
when necessary.
C.
To successfully transition from the sales team to the delivery team.
D.
To provide an adequate foundation for the Project Management Plan.
Explanation:
Project Execution and Control runs concurrently with the Implement focus area phases. The purpose
of the Project Execution and Control Phase is to provide adequate visibility into actual progress so
that management can take effective actions when the project’s performance deviates significantly
from the project plans. The Project Execution and Control Phase includes tracking and reviewing the
projects accomplishments and results against documented WBS, project estimates, time schedule,
resources plan, and cost budget, and adjusting these plans based on the actual accomplishment and
results.