Which is true about OUM Manage?
A.
It emphasizes clearly documenting the scope of the project and the exact procedures to
implement changes to this scope.
B.
It is not possible to control the project timeline without a detailed project plan.
C.
It is necessary to only document the items in the scope.
D.
If the project sponsor requires a functional change, the project team must comply with the
request.
Explanation:
The Manage focus area is organized into 13 processes:
• Bid Transition
(A) Scope Management
• Financial Management
• Work Management
• Risk Management
• Issue and Problem Management• Staff Management
• Communication Management
• Quality Management
• Configuration Management
• Infrastructure Management
• Procurement Management
• Organizational Change Management
Collectively, these processes form a comprehensive set of tasks required to manage Oracle-based
development and implementation projects. Every project includes most, if not all, of these
processes, whether they are the responsibility of a consulting organization, a client organization, or a
third party.