What is true about the Work Management Plan?
A.
It outlines the major milestones of the project.
B.
It is a document produced during the contract process.
C.
It documents the strategy, control processes, and policies that are used to manage, support, and
implement the work during the project.
D.
It is produced by the Configuration Management team.
E.
It defines the competencies of the project team.
Explanation:
Note:
* The purpose of the Work Management Plan is to establish procedures for defining, monitoring,
and directing all work performed on the project.
* The Work Management Plan should clearly state the procedures for defining, documenting,
gaining agreement on, and communicating the project’s work plan and the processes to be used for
which the plan would be executed and controlled.
The project work plan is the hub of project management as it denotes all activities that the team will
be participating in within the project’s scope, objectives, and approach and it provides a repository
of data that the project manager can utilize to manage the project to plan. Processes that would be
used for work plan execution and control would include the following:
• Developing the Baseline Project Work Plan
• Controlling the Work Plan through the life cycle of the project.
• Executing the Work Plan
• Managing Team Work
• Managing Team Time