Select the three major activities in the Project Closure phase.
A.
Manage Project Workplan
B.
Gain Acceptance
C.
Complete Project Management Plan
D.
Close Processes and Contract
E.
Document Lessons Learned and Archive Project
F.
Customer Acceptance
Explanation:
* The Project Closure phase occurs after the Production phase. During this phase, the project is
“closed” from an administrative and contractual standpoint. This includes making sure that theproject work products are complete and meet the customer’s expectations; gaining final acceptance
(F); and securing all documents (E) for reuse, collection and retention.
* Project Closure Phase is the last phase of the Project Life Cycle. The commencement of the Project
Closure Phase is determined by the completion of all Project Objectives and acceptance of the end
product by the customer. Closure of any financial issues,Collection and Completion of All Project
Records & Archiving of All Project Records are typical elements of this phase.
Should be B, D, E.
KEY CLOSURE ACTIVITIES
1. Gaining project acceptance
2. Closing the project processes and contract (releasing staff and physical resources)
3. Documenting lessons learned and archiving the project
4. Communicating