At the end of iteration phase, during Project Execution and Control, which three key tasks should be
conducted?
A.
QM.050 Perform Quality Assurance
B.
WM.050 Manage Approvals
C.
CMM.030 Manage Project Team Communication
D.
PKM.020 Conduct Baseline Risk Assessment
E.
SM.060 Close Scope management
F.
PKM.060 Conduct Post-Production Risk Assessment
G.
OCHM.040 Establish Follow-Up process
Explanation:
Note:
Incorrect:
Not D: Belongs to project start upNot E: Belongs to project closure.
Not F: Belongs to project closure.
Not G: Belongs to project closure.