Select the two plans that are always active in the project at any given time.

Select the two plans that are always active in the project at any given time.

Select the two plans that are always active in the project at any given time.

A.
Transition Plan

B.
Training Plan

C.
Implementation Plan

D.
Iteration Plan

E.
Inception Plan

Explanation:

There are two plans active in the project at any given time – the implementation plan and the
iteration plan.