What describes the initial Iteration Plan for the Inception phase?
A.
It is a static plan, which is set during Bid Transition.
B.
It is created in the Project Startup Phase.
C.
It focuses on the milestones for the Elaboration Phase.
D.
It is not needed because Inception is a short phase.
Explanation:
Note:
The overriding goal of the Inception phase is to gain concurrence among all stakeholders on the
lifecycle objectives for the project. The Inception phase is critical for all projects because the scope
of the effort, the high-level requirements, and the significant risks must be understood before the
project can proceed. The Inception phase is used to kick off a project; review the strategic direction
of the business; and confirm, document, and prioritize the high-level business requirements for the
project.
It is also the time to begin assembling and integrating the project team, to scope the entire
engagement, and develop the initial project plan.