Which two statements are true about planning in OUM?

Which two statements are true about planning in OUM?

Which two statements are true about planning in OUM?

A.
A work product is always included for every task in the project workplan.

B.
Unnecessary tasks can be eliminated from the project workplan.

C.
Each task in OUM needs to be included in the project workplan.

D.
Tasks can be combined depending on the scope and risk of the project.

E.
Tasks can be eliminated when there is no staff assigned to them.

Explanation:

B (not C): Example:
Our next step is to eliminate activities/tasks that are not needed. Consider the following:
1. Don’t eliminate anything in the Core Workflow without carefully consideration.
2. Review any available supplemental guidance.
3. Consider removing activities/tasks NOT included in the Estimate and/or Proposal.
4. Determine if it’s possible to eliminate all if not most of some processes. For example,
consider removing the following processes and corresponding activities and/or tasks, if your project
does not include ANY requirements for them:
• Performance Management
• Organizational Change Management
• Training

• Data Acquisition and Conversion
D: Finally, you should consider whether it is advisable or appropriate to combine tasks or to execute
your project using OUM’s activities – which are groupings of tasks.