Which statements are true about the active plans a project?

Which statements are true about the active plans a project?

Which statements are true about the active plans a project?

A.
There are two iteration plans – one for the current iteration and a draft for the upcoming
iteration.

B.
A subsequent iteration plan is created prior to the iteration beginning.

C.
The iteration plan for each iteration is set and cannot be altered.

D.
The project Management Plan is a document and is not affected by the implementation Plan.

Explanation:

AB (not C): During each iteration, the current Iteration Plan is adjusted. Subsequent Iteration Plan is
created prior to the iteration beginning.
Note:
* there are two plans active in the project at any given time – the implementation plan and the
iteration plan.