Which statements are true about the active plans a project?
A.
There are two iteration plans – one for the current iteration and a draft for the upcoming
iteration.
B.
A subsequent iteration plan is created prior to the iteration beginning.
C.
The iteration plan for each iteration is set and cannot be altered.
D.
The project Management Plan is a document and is not affected by the implementation Plan.
Explanation:
AB (not C): During each iteration, the current Iteration Plan is adjusted. Subsequent Iteration Plan is
created prior to the iteration beginning.
Note:
* there are two plans active in the project at any given time – the implementation plan and the
iteration plan.