What work product, created by the Project Manager and the client, details the approach to the
project at a high level?
A.
Project Management Framework
B.
Project Implementation Framework
C.
Project Resource Framework
D.
Project Work Framework
E.
Project Management WBS
Explanation:
Activities allow the project manager to streamline creation and management of the Work
Breakdown Structure (WBS) for an engagement.
Note:
* Project managers use OUM to make sure they and their stakeholders develop a shared
understanding of what is needed, choose an appropriate architecture, and transfer the ownership of
the end-product to the stakeholders.
Should be A?
WBS is not that…
The project manager creates the project management framework along with the client. At this point in the project, the Project Management Framework represents the PMP at the strategic level.