What is not true about risk management in OUM Manage?

What is not true about risk management in OUM Manage?

What is not true about risk management in OUM Manage?

A.
The project manager should regularly conduct risk assessments.

B.
Risks become even more critical during the Project Execution and Control Phase.

C.
Particular attention should be paid to risks prior to production cutover.

D.
If a baseline risk assessment is done during the Project Startup phase, there are no further risk
assessment required on the project.