Which statement is true about the Project Management Plan and the Project Workplan in OUM?
A.
They are the same document.
B.
A change to one may necessitate a change to the other.
C.
The Project Management Plan does not change after Project Startup, while the Project Workplan
may change at anytime.
D.
The Project Workplan and Project Management plan have no Impact on one another.
Explanation:
* OUM Manage provides the framework for consistently managing a project regardless of the
project approach. The project manager must be familiar with the project approach being used, and
must make the necessary adjustments in the Project Management Plan (as well as in the Project
Workplan) to incorporate the concepts and activities that support the given approach.
The same concepts apply to projects using offshore resources or third parties.
* OUM Manage and Other Project Approaches OUM Manage can be used with any project
approach. OUM Manage does not required any specific project approach. The project manager
should adjust the Project Management Plan and Project Workplan in order to execute the project
following the designated project approach.