Which three statements are true about the various plans used In OUM during Project Execution Control.

Which three statements are true about the various plans used In OUM during Project Execution
Control.

Which three statements are true about the various plans used In OUM during Project Execution
Control.

A.
Once created, the implementation Plan is never updated.

B.
The subsequent Iteration Plan is created prior to the beginning of the next iteration.

C.
The Project Management Plan should be updated, as appropriate.

D.
The subsequent Iteration Plan is created as soon as possible after the Iteration begins.

E.
The current Iteration Plan is adjusted, as appropriate.

Explanation:

B: Subsequent Iteration Plan is created prior to the iteration beginning.
E: During each iteration, the current Iteration Plan is adjusted.
Note:
* There are two plans active in the project at any given time – the implementation plan and the
iteration plan.