which process is started and completed within a single phase?

In the OUM Manage Focus Area, which process is started and completed within a single phase?

In the OUM Manage Focus Area, which process is started and completed within a single phase?

A.
Bid Transaction

B.
Scope management

C.
Risk Management

D.
Project Closure

Explanation:

A: Bid Transition The Bid Transition process, Typically represented in Project Start Up, is in reality
more of a project initiation task. The first major activity that a project manager is expected to
perform is to participate in the handoff from the “sales cycle” to the “delivery cycle”.
Incorrect:
Not B: Scope Management – The goal of the Scope Management process is to identify clear
boundaries of what is to be implemented and what key work products are to be produced.
Not C: Risk Management – Risk Management is a structured process for identifying, documenting,
gaining agreement on, and communicating risks throughout the lifecycle of a project.



Leave a Reply 1

Your email address will not be published. Required fields are marked *


Margarita

Margarita

Addition: Not D because “project closure” is not a process within Manage Focus Area, it i a phase itself.

Initially I thought it could be D, but in this case question would need to be reformulated since there is a list of defined processes for OUM Manage…