What is the most important aspect of closing the project?
A.
Successful go-live.
B.
End-user training is complete.
C.
Project Team finds new assignments.
D.
Formal client acceptance is gained.
Explanation:
The Project Closure phase occurs after the Production phase. During this phase, the project is
“closed” from an administrative and contractual standpoint. This includes making sure that the
project work products are complete and meet the customer’s expectations; gaining final acceptance
(D); and securing all documents for reuse, collection and retention.