Which three statements are true about the Validated Scope of the project?
A.
It uses outputs of the Bid Transition process as a prerequisite.
B.
It documents the boundaries of the project.
C.
It documents only contractual deliverables.
D.
It documents the contents of the Work Breakdown Structure.
E.
It is a key input to the Project Management Plan.
Explanation:
B: Scope Management – The goal of the Scope Management process is to identify clear boundaries
of what is to be implemented and what key work products are to be produced.
D: A work breakdown structure permits summing of subordinate costs for tasks, materials, etc., into
their successively higher level “parent” tasks, materials, etc. For each element of the work
breakdown structure, a description of the task to be performed is generated. This technique
(sometimes called a system breakdown structure) is used to define and organize the total scope of a
project.