Which three items must be updated when scope changes are approved?

Which three items must be updated when scope changes are approved?

Which three items must be updated when scope changes are approved?

A.
Project scope

B.
Project budget

C.
Project component value ratio

D.
Project cost center

E.
Project schedule

Explanation:

Note:
Project scope is the part of project planning that involves determining and documenting a list of
specific project goals, deliverables, tasks, costs and deadlines.