What is one of the first outputs of the Project Execution and Control Phase?

What is one of the first outputs of the Project Execution and Control Phase?

What is one of the first outputs of the Project Execution and Control Phase?

A.
Staff retention plan

B.
Team orientation and kickoff

C.
Project sponsor orientation and kickoff

D.
Go-live cutover

E.
Contract sign-off

Explanation:

Note:
The purpose of the Project Execution and Control Phase is to provide adequate visibility into actual
progress so that management can take effective actions when the project’s performance deviates
significantly from the project plans. The Project Execution and Control Phase includes tracking and
reviewing the projects accomplishments and results against documented WBS, project estimates,
time schedule, resources plan, and cost budget, and adjusting these plans based on the actual
accomplishment and results.