What is the basis for the Project Management Plan [PMP]?

What is the basis for the Project Management Plan [PMP]?

What is the basis for the Project Management Plan [PMP]?

A.
the Project Framework

B.
the project deliverables

C.
the resourcing plan

D.
the procurement plan

Explanation:

The creation of the PMP is started with the Project Management Framework in the task BT.070 –
Create Project Management Framework, which is part of the OUM Manage Focus Area’s Project
Startup Phase. The project manager creates the Project Management Framework, along with the
project sponsor and other stakeholders. At this point in the project, the Project Management
Framework represents the PMP at the strategic level. In fact, the Project Management Framework
can be thought of as the initial or high-level version of the PMP.