You need to resolve the overallocations by using the Resource Leveling function

You are a project manager who uses Project Professional 2013. All resources in your project
schedule have availability of 8 hours per day. You notice that several of the resources on the project
are overallocated. You decide to level the project to help resolve the overallocations for the
resources. Team members often do not work at the same time when completing their work on the
tasks. You need to resolve the overallocations by using the Resource Leveling function. What should
you do?

You are a project manager who uses Project Professional 2013. All resources in your project
schedule have availability of 8 hours per day. You notice that several of the resources on the project
are overallocated. You decide to level the project to help resolve the overallocations for the
resources. Team members often do not work at the same time when completing their work on the
tasks. You need to resolve the overallocations by using the Resource Leveling function. What should
you do?

A.
Click the Level only within available slack option.

B.
Click Clear Leveling.

C.
Click the Leveling can adjust individual assignments on a task option.

D.
Click the Level resources with a proposed booking type option.