Which three variables are used with Earned Value?

Which three variables are used with Earned Value?

Which three variables are used with Earned Value?

A.
EV – Earned Value

B.
PV – Planned Value

C.
AC – Actual Cost

D.
PC – Planned Cost

E.
EC – Earned Cost

F.
AC – Accounting Cost

Explanation:

EV – earned value, estimated value of work done.
PV – planned value, estimated value of planned work
AC – actual cost, what you paid